Our Planned Maintenance Programme for the period 2019/20 to 2023/24 is set out below. The actual year that work will be carried out may need to change if we have to delay or bring forward works for operational reasons. The exact scope and extent of works in each project is also subject to survey and agreement with any private owners involved. To see the work planned, click on the year or scroll down:
2020/21 programme – total spend £2.36m
Project | Homes | Areas covered |
---|---|---|
Internal works Partial or full replacement of kitchens and bathrooms (subject to survey) |
100 | Various Locations – delayed due to COVID-19 |
External works Replacement windows, roofs, rainwater goods, chimney removals, re-render and fencing |
140 (inc 18 owners) |
28 Fintryside (6) – delayed from 2019/2020 due to Covid-19 30 Fintryside (6) – delayed from 2019/2020 due to Covid-19 4 Findale Street (6) – delayed from 2019/2020 due to Covid-19 4a Findhorn Street (6) 77 Findowrie Street (1) Kingsway West (7) 2 – 18, 22-26 Grampian Gardens (108 incl 18 owners) |
Electrical Upgrades Bringing electrical wiring and fitment in homes up to modern standards |
49 | Various Locations – delayed due to COVID-19 |
Painterwork Rolling 7year programme. |
257
(in 48 owners) |
Fintry AI (37) – Finavon Pl, Findcastle Terr Fintry P1 (91) – Fintry Dr, Fintry Mains Fintry H1 (5) – FInella Gdns Fintry H2 (5) – Fintry Dr Fintry G2 (13) – Findcastle St, Fintry Dr Fintry P2 (6) – Fintry Road Fintry G1 (11) – Finedon Terr, Fintry Cres Fintry I1 (7) – Fintry Dr Fintry J1 (4) – Fintry Rd, Finavon Terrace Fintry K1 (42) – Fintry Rd Fintry L1 (36) – Fintry Cres |
2021/22 Programme – total spend £2.50m
Project | Homes | Areas covered |
---|---|---|
Internal works Partial or full replacement of kitchens and bathrooms (subject to survey) |
0 | None planned |
External works Replacement windows, roofs, rainwater goods, chimney removals, re-render and fencing |
— | Under review due to COVID-19 |
Painterwork Rolling 7year programme. |
325 | Finlaggan Crescent Fintry Crescent (1 – 11) Fintryside (79 – 112) Fintry Road (1 – 7) Caldrum Street |
2022/23 programme – total spend £2.40m
Project | Homes | Areas covered |
---|---|---|
Internal works Partial or full replacement of kitchens and bathrooms (subject to survey) |
0 | None planned |
External works Replacement windows, roofs, rainwater goods, chimney removals, re-render and fencing |
— | Under review due to COVID-19 |
Painterwork Rolling 7year programme. |
Tbc | Various |
2023/24 programme – total spend £3.23m
Project | Homes | Areas covered |
---|---|---|
Internal works Partial or full replacement of kitchens and bathrooms (subject to survey) |
0 | None planned |
External works Replacement windows, roofs, rainwater goods, chimney removals, re-render and fencing |
— | Under review due to COVID-19 |
Painterwork Rolling 7year programme. |
Tbc | Various |