Our Planned Maintenance Programme for the period 2019/20 to 2023/24 is set out below. The actual year that work will be carried out may need to change if we have to delay or bring forward works for operational reasons. The exact scope and extent of works in each project is also subject to survey and agreement with any private owners involved.  To see the work planned, click on the year or scroll down:

2020/21 programme – total spend £2.36m

Project Homes Areas covered
Internal works
Partial or full replacement of kitchens and bathrooms (subject to survey)
100 Various Locations – delayed due to COVID-19
External works
Replacement windows, roofs, rainwater goods, chimney removals, re-render and fencing
140
(inc 18 owners)
28 Fintryside (6) – delayed from 2019/2020 due to Covid-19
30 Fintryside (6) – delayed from 2019/2020 due to Covid-19
4 Findale Street (6) – delayed from 2019/2020 due to Covid-19
4a Findhorn Street (6)
77 Findowrie Street (1)
Kingsway West (7)
2 – 18, 22-26 Grampian Gardens (108 incl 18 owners)
Electrical Upgrades
Bringing electrical wiring and fitment in homes up to modern standards
49 Various Locations
Painterwork
Rolling 7year programme.
257

(in 48 owners)

Fintry AI (37) – Finavon Pl, Findcastle Terr
Fintry P1 (91) – Fintry Dr, Fintry Mains
Fintry H1 (5) – FInella Gdns
Fintry H2 (5) – Fintry Dr
Fintry G2 (13) – Findcastle St, Fintry Dr
Fintry P2 (6) – Fintry Road
Fintry G1 (11) – Finedon Terr, Fintry Cres
Fintry I1 (7) – Fintry Dr
Fintry J1 (4) – Fintry Rd, Finavon Terrace
Fintry K1 (42) – Fintry Rd
Fintry L1 (36) – Fintry Cres

2021/22 Programme – total spend £2.50m

Project Homes Areas covered
Internal works
Partial or full replacement of kitchens and bathrooms (subject to survey)
0 None planned
External works
Replacement windows, roofs, rainwater goods, chimney removals, re-render and fencing
Under review due to COVID-19
Painterwork
Rolling 7year programme.
325 Finlaggan Crescent
Fintry Crescent (1 – 11)
Fintryside (79 – 112)
Fintry Road (1 – 7)
Caldrum Street

2022/23 programme – total spend £2.40m

Project Homes Areas covered
Internal works
Partial or full replacement of kitchens and bathrooms (subject to survey)
0 None planned
External works
Replacement windows, roofs, rainwater goods, chimney removals, re-render and fencing
Under review due to COVID-19
Painterwork
Rolling 7year programme.
Tbc Various

2023/24 programme – total spend £3.23m

Project Homes Areas covered
Internal works
Partial or full replacement of kitchens and bathrooms (subject to survey)
0 None planned
External works
Replacement windows, roofs, rainwater goods, chimney removals, re-render and fencing
Under review due to COVID-19
Painterwork
Rolling 7year programme.
Tbc Various